It’s the beginning of the end for Swindon Panel…. but the beginning of the beginning of its preservation!
The August bank holiday weekend (2014) was, at one point, to be the date that Swindon Panel closed (this was the second planned date, the first was in May 2014).
The Swindon Panel area (except the Kemble Line) is to be ‘re-locked’ and ‘re-controlled’. ‘Re-locked’ as a new solid state interlocking would be provided to interlock the points and signals, replacing Swindon Panel’s current nine electromechanical interlockings, and ‘re-controlled’ as the system would be controlled from the Thames Valley Signalling Centre in Didcot, instead of Swindon Panel as currently. This is slightly different from a ‘re-signalling’, as the layout of points and signals on the ground will be largely the same as it currently is, so apart from changes to the numbers on the signals, and a few minor alterations to spacing, the system will appear generally the same to drivers.
In tandem with the re-lock and re-control taking place, the single line between Swindon Loco Yard and Kemble was due to be re-doubled and re-signalled. Although a separate project, this was due to take place at the same time.
Unfortunately, delays in the installation of the required equipment for the completely new signalling system meant that the entire panel area was not ready for resignalling in August, and the panel closure was deferred (as reported in earlier newsletters). The Kemble Line work, however, could not be deferred any longer. So this work DID take place over the bank holiday weekend.
Minety Crossing Box was due to close on Friday 1 August, but issues with the signalling circuitry design meant that, even though the highway was closed, the crossing box stayed open until 9 August 2014. On 9 August the crossing box closed and the signals were removed (MX1, MX1R, MX2, MX2R). Trains ran with the highway closed like this for a further 8 days.
The last Kemble Line train signalled by Swindon Panel was 2B99, 2201 (Mon) Cheltenham Spa to Swindon on Monday 18 August. (The last down train was 2G93). The line was then taken under engineer’s possession. At 0108 on Tuesday 19 August the Kemble signalling power supply was switched off. The signals went black, the panel went red, and the Kemble Line was gone from Swindon Panel forever. 27 July 1968 – 19 August 2014. 46 years and three weeks of service to Swindon MAS.
The heavy work then started, as track engineers worked to bring the new second track into service. At the Swindon Loco Yard end the double-to-single points were decommissioned and the up line slewed to its new formation to meet the newly-laid Up Kemble line. The crossovers at Rodbourne Jn had been laid in and out of use since some months before. At the Kemble end of the line the double-to-single points were decommissioned and the down line slewed to its new formation to meet the newly-laid Down Kemble line, just north of Kemble Tunnel. (The line being used as the ‘single’ changed from up to down along the way).
The new crossover at Kemble was brought into use. The crossovers at Rodbourne remain out of use for the time being.
Swindon Panel’s signals were removed and new signals for TVSC uncovered. The new signals have a prefix ‘SW’ (for SWindon area).
As a rough comparison, on the Down Kemble:
SN.44/46/48 from Swindon Station towards Kemble.
SW.1313, [replaces SN.150] stop signal (R/G), at Swindon Loco Yard.
SW.1319, new repeater signal (Y/G), for SW.1321.
SW.1321, new stop signal (R/G) near Bentham.
SW.1325, [replaces MX.1R] repeater (Y/G) for SW.1327, for Minety signal.
SW.1327, [replaces MX.1] stop signal (R/G), protecting signal for Minety LC.
SW.1331, [replaces SN.158R] repeater (Y/G) for SW.1333
SW.1333, [replaces SN.158] stop signal (R/Y/G + DA + JI 4), protecting Kemble Tunnel and station
SW.1337, [replaces SN.160] stop signal (R/G).
DK.94R, DK.94, Gloucester’s first automatic, as previously.
On the Up Kemble:
UK.94, Gloucester’s last automatic, as previously.
SW.1340, [replaces SN.147R] repeater (Y/G) for SW.1338
SW.1338, [replaces SN.147], stop signal (R/Y/G) protecting Kemble Station
SW.1334, [replaces SN.149], stop signal (R/G), on the end of the up platform at Kemble.
SW.1330, [replaces MX.2R], repeater (Y/G) for SW.1328 at Minety.
SW.1328, [replaces MX.2], stop signal (R/G) protecting Minety LC.
SW.1324, new repeater signal (Y/G) for SW.1322.
SW.1322, new stop signal (R/G) near Bentham.
SW.1318, [replaces SN.157R], near Moredon, repeater signal (Y/G) for SW.1316.
SW.1316, [replaces SN.157], stop signal (R/Y/G), protecting Rodbourne Jn.
SN.159, as previously.
Train detection is now by axle counters throughout. There has been a fairly long axle counter section between Moredon and Kemble Wick since 1989 (0600 on Monday 29 May 1989 to be precise!). This was provided due to the unreliability of the very long, multi-section track circuit that preceded it.
A new Alstom Smartlock interlocking fitted by Signalling Solutions and controlled by a Delta Rail IECC workstation was provided at TVSC to control the new signalling. At 0453 on Bank Holiday Monday 25 August the possession was withdrawn, and at 0500 the Swindon Workstation in TVSC opened for business. The first train signalled was 2Z22, 0529 Cheltenham Spa to Swindon. It ran on time (or 1E) all the way. If you have visited TVSC on one of our visits, the new Swindon desk it so the left of the Didcot desk.
Minety Level Crossing is still closed to road traffic (due to be commissioned on 28th August) as a CCTV level crossing (formerly manual gates), controlled from the Level Crossing workstation in TVSC.
Purton Common user-worked crossing was due to be upgraded to miniature red and green lights, but this has also not yet happened and the crossing remains as a UWC+T for the time being.
Another footpath crossing, Clovers, has been upgraded from UWC to UWC+T with the fitting of telephones for users. Gambols Farm and Gryphon Lodge remain as UWC+T.
The ground frame controlling access to the siding at Kemble survives(!) The Annett’s key now being released from the IECC.
Trains can now be turned-back in both directions at Kemble, by either arriving from Swindon in the up platform by means of the new facing crossover and changing ends, or arriving from Gloucester in the up platform and shunting to a Limit of Shunt on the Down Kemble south of the tunnel via the facing crossover, then back into the down platform.
The fringe between Swindon Panel and TVSC is easy to manage on the down, as Swindon Panel signal trains to their last exit button in rear of TVSC’s SW.1313, and TVSC control that signal, just like any other TCB fringe.
On the up, however, there being points in the overlap of Swindon Panel’s first signal (SN.159), TVSC has to be a little careful clearing their last signal (SW.1316) to avoid ‘snookering’ Swindon Station. For example, a down train leaving platforms 1 or 2 towards Kemble cannot depart while a train is signalled up to the signal immediately outside the station, SN.159, which is now Swindon Panel’s first signal. There are also routes on Swindon Panel to a limit of shunt in the overlap of SN.159! To combat all this, Swindon Panel has been provided with a slot in the equivalent position to SN.157, which controls TVSC’s last signal, SW.1316. This allows Swindon Panel to maintain flexibility in Swindon station with Kemble-bound trains on platforms 1, 2 and 3, while maintaining safety against the conflicting moves.
In Swindon Panel the panel tiles for the Kemble line have been removed or covered over and, of course, rescued for ultimate re-insertion into the panel in preservation. We are extremely grateful to Network Rail and their contractors for minimising the wiring alterations to the panel in the course of this work, including leaving the majority of the panel wiring in place for us. The only wiring alterations that have taken place are in connection with the provision of the slot switch.
The date for the migration of the rest of Swindon Panel to TVSC remains in the air – the ‘first part of 2015’ is the current official estimate…..
Fascinating post – thanks!
When you say “Swindon Panel’s signals were removed and new signals for TVSC uncovered” do you mean that all of the signal posts (with the lamps in them etc) were replaced? Was this necessary because the TVSC equipment couldn’t work with the old signals? Or the opportunity just taken to upgrade the signals (presumably to LED lamps?) at the same time as this work?
Hello
Most of the signals were replaced with new ones.
I imagine it was just a good time to upgrade everything to new equipment instead of battling on with the 1960s stuff.
Danny S.
hello,
Last wednesday i had a ride up and down this line and noticed the sets of temporary points at the swindon end had gone.
trains use to come out of swindon over a rather shabby set of points( and still do) to a straight run over onto one line and over a new set, still there and up a new stretch of track, brought into use in april.
i assume at the swindon end the old crossovers on a curve to plats 1 2 3 will be removed and replaced with new sections of track which is part still jointed.
The new crossovers at Roudbourne Jn are not yet in use (but they are still present).
The now-facing crossover was secured in reverse until the commissioning as the ‘single’ line changed from side to side.
The crossover points on the sharp curve at Swindon West will be removed and the new crossovers at Rodbourne will come into use when the rest of Swindon Panel closed.
– Danny S.
Well done with this summary, Danny.
Just one correction – Purton Common LC is a public bridleway. Yes, until the S&T can commission the MSLs it will continue as a passive LC with horseriders instructed to phone.
The new signal sections are a great benefit to callers from here and from the UWCTs, because TVSC can more easily determine where trains are and of course keep signals at danger when necessary.
Cheers
Tim